Works at IPB are progressing according to schedule!

11.03.2008

The five production halls which are to be finalized by the end of 2008 at IPB, are part of Phase 1.

90% of the infrastructure works have been finalized for the first 10.000 sqm hall. The 90 reinforced concrete pillars of the future production hall are being erected, along with the 33 perimetral metall pillars.

In parallel, works for building other three future production units are in progress.

Currently, the team working for the construction of the IPB consists of 70 skilled workers and technical engineers working intensively to be ahead of time.